Network Renewal: From Project to Regular Operation

Source: Own Illustration
After several years of intensive planning and implementation work, the network renewal at RWTH Aachen University is approaching an important milestone: Since its launch in 2018, the finish line for the end of 2026 is slowly coming into view. You can also read about our interim status in 2022 in our previous blog article. The completion of the measures in the individual university buildings marks the transition from project to regular operation. The aim of the network renewal is to modernize the communication infrastructure, which is in some parts severely outdated, and to put it on a future-proof footing—technically, organizationally, and operationally.
4 Years of Network Renewal
A Look Back From a Coordinator’s Point of View
Was it really four years ago that our boss announced with beaming eyes that the application for network renewal had been approved?
Expanding the data network and WLAN, and switching to a new telephone system – in all RWTH buildings. It sounded too fantastic…and yet it came true.
Over the next few days, we stood together again and again in small groups and thought about how we could manage such a huge project. And shortly after that, I was sitting in meetings with the coordinator’s cap on my head, because all of our processes and procedures had to be discussed and adjusted. A huge jolt went through the entire department “Networks”, because everyone wanted to take on this challenge and try to get involved so that we could accomplish this enormous task.